|
|
Section
03252 / Section 03300 / Section 07900 (Cross Reference) SPECIFICATION
FOR AMBIENT TEMP SPAL-PRO 2000 INSTALLATION PART 1 - GENERAL1.01 General Description of Work Provide
all labor, products and equipment required to properly install semi-rigid filler
in joints in the interior concrete floor slabs. 1.02.
Scope of Work Fill
all contraction (control) and construction (formed) joints in the interior
concrete floor slab where the joints will be exposed to material handling
vehicle wheels. Refer to drawings for additional joints possibly requiring
filler, such as joints under racks,joints at column diamonds and pads, etc. 1.03.
Work Excluded This
section specifically excludes all caulking and sealant work specified in Section
7900. Refer to 7900 to determine 1.04.
Applicable Standards Products
and installation shall be in compliance or exceed the joint filling criteria
established in the latest ACI 302 and ACI 360 Committee published documents and
all manufacturers instructions and technical literature. 1.05
Contractor Qualifications Installer
shall have a minimum of three (3) years experience in the installation of
semi-rigid fillers on industrial floors. 2. PRODUCTS 2.01
Product(s) Joint
filler shall be Spal-Pro 2000, a heavy duty, semi-rigid polyurea manufactured by
Metzger/McGuire, Concord, NH (800-223-6680). No substitutes will be allowed.
Material shall be brought to site in original, unopened containers. Product will
be stored in temperatures between 50-80 degrees F. 2.02
Accessories Silica
sand may be used at contractor’s option to choke-off 3. EXECUTION 3.01
Project Conditions Work
area should be free of obstructions and other trades. Slab should be visibly dry
and not be scrubbed for at least 24 hours prior to filler installation. Air
temperature should be greater than 40 degrees F for 24 hours prior to filling. 3.02
Timing of Installation ACI
recommends that filling be deferred as long as possible to allow for maximum
slab shrinkage and joint widening. 90-120 day slab cure is advisable. Deferring
filling until after facility is under permanent temperature control is best. 3.03
Examination of Conditions It
is the responsibility of the installer to inspect the project and joint
conditions and notify on-site management in writing of any deficiencies that
might adversely affect the quality or durability of the work performed or his
contract price. Start of work by the installer implies acceptance of conditions. 3.04
Pre-Installation Sample Before
start of actual work contractor shall install samples to demonstrate his
intended procedures and finished product. Sample shall include at least 25’
each of both contraction and construction joints in the presence of on-site
management. If procedures and finished product are approved they will be
considered a standard for the entire project. 3.05
Joint Preparation All
saw-cut joints shall be thoroughly cleaned to their full depth or 2” minimum,
whichever is lesser. Construction (formed) joints that are not sawn shall be
cleaned to a minimum depth of 2”. Preparation shall be performed using a
vacuum-equipped saw that will reach the 2” minimum depth, and shall be used in
a manner that takes both joint walls back to bare concrete, removing all saw
laitance, curing compounds, sealers, debris, etc. Where joints have minor edge
chips, said chips will be “squared off” and filled along with the joint
itself. 3.06
Choking-Off Joint Bottom The
installer may, at his option, use a maximum of 1/4” of silica sand placed at
the bottom of the saw-cut joints to prevent filler run-thru into the shrinkage
crack. Compressible backer rod is prohibited in saw-cut joints unless they
exceed 2” deep. Compressible backer rod may be used in through-slab(non-sawn)
construction joints but must be recessed at least 2” below the slab surface. Caution: The use of backer rod in any saw-cut joints less than 2” deep will result in the rejection of all saw-cut joints work. 3.07
Filler Installation
a. Properly clean joints as described in section 3.05
b. Install silica sand (contractors option) at base of
joint, or backer rod as allowed and limited in 3.06.
c. Pre-mix the “A” component to re-disburse any
settlement that occurred in shipping or storage.
d. Due to it’s rapid gel time Spal-Pro 2000 must be
dispensed via power pump (dual-feed line system) or
from dual-cartridge units pre-packaged by
Metzger/McGuire.
e. Dispense Spal-Pro 2000 in one continual bead, filling
from bottom to top until joint is overfilled (crowned).
Allow to cure into a solid.
f. After Spal-Pro 2000 cures into a solid, razor-off
overfill to leave a flush filler profile.
A
flush filler profile is vital for maximum joint protection. If profile is
concave (below floor surface), abrade Spal-Pro 2000 surface and apply a cap bead
(crowned), allow to cure, then razor flush. |